CERCLA Remedial Action Site Closure Guidance
Figure 3. Type A: Clean Closure for CERCLA Operable Units
Contents:
III-A. Type A: Clean Closure
This section discusses the types of remedial actions that can occur
at a CERCLA
operable unit. For purposes of explanation, most CERCLA
remedial actions can be organized in three categories or ‘types’
at the operable unit level. These three types are: Type A, ‘Clean
Closure,’ Type B, ‘Long-Term Cleanup,’ and Type
C, ‘Waste-in-Place.’
Type A addresses a typical excavation and off-site disposal remedial
strategy or ‘clean closure’ for CERCLA operable units.
Excavation and off-site disposal is a time tested and well-proven
technology where contaminated material is removed and transported
to permitted off-site treatment and/or disposal facilities. Prior
to 1984, excavation and off-site disposal was the most common method
for cleaning up hazardous waste sites. In most situations, the remedial
action is completed within five years and the selected remedy will
not place restrictions on the potential use of land or other natural
resources (i.e., the remedy achieves unlimited use and unrestricted
exposure). Therefore, there are no five-year reviews or post-remediation
care activities associated with this scenario. Figure 3 depicts
the standard CERCLA remedial action completion elements for the
excavation and off-site disposal strategy. To find out more about
these requirements, simply click on the section of the process that
is of interest to you.
A.1 Remedial Action (RA)
The RA is the implementation of the remedy selected in the Record
of Decision (ROD). The RA
start date is defined as the date the contractor has mobilized and
begun substantial and continuous physical on-site remedial action,
as documented by a memo or letter to EPA.
A.2 Final Inspection [top]
With any RA
construction contract, normal construction industry practice is
to conduct contract pre-final and final inspections prior to closing
out the construction contract. These inspections are conducted to
determine whether the construction has been completed in accordance
with the contract design and specifications.
During the pre-final inspection, the contracting party’s
project manager and the construction contractor inspect all elements
of work to see if the work is complete and ready for acceptance
under the terms of the contract. Some minor defects may come to
light. The construction manager develops a “punch list”
of all items that need correction or completion before the work
can be accepted. A pre-final inspection report is prepared, including
the punch list, completion dates for outstanding items, and a date
for the final inspection.
If punch list items are minor, the pre-final inspection may automatically
serve as the final inspection. Otherwise, a final inspection is
conducted later to determine that punch list items are corrected
and all work has been completed in accordance with the contract
plans and specifications.
Federal Facility Agreements (FFAs) generally require a set of inspections
to determine that all aspects of the remedy have been implemented
in accordance with applicable enforcement documents and the ROD.
Participants for the final inspection usually include: DOE, the
State, EPA, and the DOE oversight contractor.
A.3 Final Remedial Action Report [top]
If the remedy in the Record of Decision (ROD) requires excavation
and off-site disposal and this results in the unrestricted use of
the property, then the CERCLA
milestone at the operable unit is completion of the Remedial Action
Report (RA Report). Once all wastes have been excavated and removed
from the site to an approved location and the cleanup goals have
been achieved (as specified in the ROD),
then the RA Report is submitted to the designated EPA Regional Official.
There are no other CERCLA milestones for this particular operable
unit after submission and approval of the RA Report because there
is no operation and maintenance or post-remediation activities required.
The site has been cleaned up to unrestricted use.
A.4 Preparing the Final RA
Report [top]
DOE is the lead agency and as the lead agency DOE should prepare
the RA
Report in consultation with EPA and the State.
The RA
Report usually contains ten sections and these sections should be
tailored to the operable unit depending upon the type of remediation
used. For example, Section VII, ‘Operation and Maintenance,’
activities would not apply for excavation and off-site disposal.
The sections in the report are as follows:
A.5 Submitting the Final RA
Report to EPA [top]
Following completion of the final contract inspection, submit the
Final RA
Report to the designated EPA Regional Official.
When the report is received at the EPA Regional Office, EPA uses
the following criteria to approve the Report:
- All construction activities are complete, including site restoration;
- All cleanup goals as specified in the ROD
have been achieved;
- A contract final inspection or equivalent has been conducted;
and
- The RA
Report is otherwise consistent with the EPA guidance, Close
Out Procedures for National Priorities List Sites.
A.6 Final RA
Report Approval [top]
EPA will return the report with the signature (of the Branch Chief
or above) on the cover sheet or by letter to DOE. At the operable
unit level, EPA Headquarters does not have to review the report
or concur with the EPA region.
Once the designated Regional EPA Official approves in writing the
RA Report, this CERCLA
milestone has been achieved.
A.7 RA
Completion [top]
RA completion for an operable unit is achieved when the designated
Regional EPA Official approves in writing the Final RA Report. For
an excavation and off-site disposal remedial action, the RA is considered
complete after:
- All wastes have been excavated and removed from the site to
an approved location
- The site has been restored;
- The cleanup goals have been achieved; and
- The Final RA Report is approved.
A.8 Checklist for Type A – Clean Closure [top]
- Remedial Action
- Pre-Final Inspection
- Punch List
- Final Inspection
- Final RA
Report
- Submitting the Final RA
Report to EPA
- Approval of Final RA
Report
- RA
Completed for Operable Unit
|