CERCLA Remedial Action Site Closure Guidance
Figure 2 Pre-Remedial Activities for CERCLA
Operable Units
Contents:
II-A Purpose
This section presents a summary of the typical activities preceding
remedial action completion of CERCLA
operable units. These activities are illustrated in Figure 2. The
information in this section is presented to provide you with an overview
of activities that have occurred (or should have occurred) prior to
remedial action. To find out more about these requirements, simply
click on the section of the process that is of interest to you or
scroll down.
II-B Remedial Investigation/Feasibility Study
(RI/FS) [top]
The CERCLA
remedial investigation/feasibility study (RI/FS) is the methodology
used to first characterize the nature, extent, and risks posed by
uncontrolled releases of hazardous contaminants, and second, to
make an informed decision for evaluating potential remedial options.
The primary steps in the RI/FS
methodology include:
- Scoping the RI/FS
- Conducting the RI:
Site Characterization
- Conducting the RI:
Baseline Risk Assessment
- Developing the RI
Report
- Feasibility Study: Development and Screening of Alternatives
- Treatability Studies
- Feasibility Study: Detailed Analysis of the Alternatives
- Developing the FS
Report
- Integrating the RI and FS Reports
In conducting the CERCLA process, DOE addresses NEPA values (such as analysis of cumulative, off-site, ecological,
and socioeconomic impacts) to the extent practicable and includes a brief discussion of impacts in CERCLA
documents or other site environmental documents as appropriate.
II-C Remedy Selection [top]
Following the detailed analysis and feasibility study of remediation
alternatives, DOE identifies a preferred alternative for the remedial
action that best meets the five statutory requirements as described
in CERCLA
Section 121:
- Protect human health and the environment;
- Attain Applicable or Relevant and Appropriate Requirements
(ARARs)
or provide reasons for not achieving ARARs;
- Be cost effective;
- Utilize permanent solutions, alternative solutions, or resource
recovery technologies to the maximum extent possible; and
- Satisfy the preference for treatment that reduces the toxicity,
mobility, or volume of the contaminants as opposed to an alternative
that provides only for containment.
In addition to the above statutory requirements for remedial actions,
the NCP
established nine ‘evaluation criteria’ [40
CFR 300.430(e)(9)(iii)] to judge each alternative. These
nine criteria are grouped by, two ‘threshold criteria,’
five ‘primary balancing criteria,’ and finally, two
‘modifying criteria.’ These criteria are based on the
CERCLA
five statutory requirements in Section
121.
II-D Proposed Plan [top]
The preferred alternative identified by DOE is presented to the
public in the Proposed Plan. A Proposed Plan is required under 40
CFR 330.430(f)(2) . The Proposed Plan describes the remedial
alternatives analyzed, identifies the preferred alternative, and
discusses the rationale for its selection. It supplements the RI/FS
report and is released for public comment along with the RI/FS
report. This provides the public with an opportunity to examine
and comment on remediation alternatives (including the preferred
alternative) and participate in the remedy selection process as
required under 40
CFR 300.430(f)(3) .
II-E Record of Decision (ROD) [top]
When the final remedy is agreed upon and selected, 40
CFR 300.430(f) requires that the decision be documented
in the ROD.
The ROD
is a formal, legal mechanism for documenting the remedy selection
process and the analyses and policy determinations that support
selection of the final remedy. Under 40
CFR 300.430(f)(5) , the ROD
must describe the following:
- How the remedy is protective of human health and the environment,
and how it eliminates, reduces, or controls exposure to hazardous
substances, pollutants, and contaminants;
- The Federal and State ARARs
the remedy will attain, those that will not be met and the justification
for waivers;
- How the remedy is cost effective; and
- How the remedy uses permanent solutions and alternative treatment
or resource recovery technologies to the maximum extent practicable.
DOE must publish a notice of availability for the ROD,
include the ROD
in the administrative record for the site, and make it available
for public inspection.
II-F Remedial Design (RD) [top]
Once the remedy is selected and the ROD
is completed, DOE will begin the design of the full-scale remedy.
Although EPA has not promulgated regulations that provide specific
requirements for the plans developed during the RD phase of a CERCLA
response, the following represent common elements to most RDs:
- Review the objectives established for the RA;
- Revise the Community Relations Plan;
- Develop an RD
Strategy Document;
- Prepare a complete set of detailed construction drawings, document
all engineering calculations, and prepare a complete set of process
flow diagrams for the RA;
- Develop a list of and specifications for all equipment and
materials required to implement the RA;
- Prepare operational guidance for the remedy;
- Develop a cost estimate and proposed schedule;
- Revise the Quality Assurance Project Plan used during the RI/FS
and Develop a Construction Quality Assurance Plan; and
- Revise the Health and Safety Plan used during the RI/FS.
Once the RD
process is complete, DOE should provide these documents to EPA and
the State for their review. These documents are usually identified
in the Federal Facility Agreement (FFA) or Consent Agreement. EPA
and the State will review and either approve or reject the documents.
Only when EPA and the State have approved the documents should actual
construction of the remedy begin.
|