CERCLA Remedial Action Site Closure Guidance
Figure 6. Typical CERCLA
Construction Completion and Site Completion Activities
Contents:
IV. Remedial Action Completion
Section IV addresses construction completion and site completion
activities that occur at the site level once the construction work
at the last operable unit has been completed. A “construction
completion” site is an NPL
site where physical construction of all cleanup activities is complete
(final cleanup goals may or may not have been achieved at this time),
all immediate threats have been addressed, and all long-term threats
are under control. By contrast, “site completion” signifies
the end of all response actions. Site completion means that cleanup
goals have been achieved and no further Superfund response is required
to protect human health and the environment. Figure 6 depicts the
standard construction completion and site completion elements at
the site level. To find out more about these requirements, simply
click on the section of the process that is of interest to you.
IV-A Remedial Action (RA) For the Last Operable
Unit [top]
The RA
is the implementation of the remedy selected in the Record of Decision
(ROD). The RA
start date is defined as the date the contractor has mobilized and
begun substantial and continuous physical on-site remedial action,
as documented by a memo or letter to EPA. As construction for the
last operable unit nears completion, DOE in cooperation with the
State and EPA should plan ahead for achieving both construction
completion and then site completion.
IV-B Pre-Final Inspection of the Last Operable
Unit [top]
With any RA
construction contract, normal construction industry practice is
to conduct contract pre-final and final inspections prior to closing
out the construction contract. These inspections are conducted to
determine whether the treatment system has been completed in accordance
with the contract design and specifications. The inspections are
generally held between the contracting party (DOE) and the construction
contractor, although others can be invited (e.g., EPA).
During the contract pre-final inspection for the last operable
unit, the contracting party’s project manager and the construction
contractor inspect all elements of work to see if the work is complete
and ready for acceptance under the terms of the contract. Some minor
defects may come to light as the inspection proceeds. The construction
manager develops a “punch list” of all items that need
correction or completion before the work can be accepted. A pre-final
inspection report is prepared, including the punch list, completion
dates for outstanding items, and a date for a final inspection.
If punch list items are minor, the pre-final inspection may automatically
serve as the final inspection. Otherwise, a final inspection is
conducted later to determine that punch list items are corrected
and all work has been completed in accordance with the contract
plans and specifications. Federal Facility Agreements (FFAs) generally
require a set of inspections to determine that all aspects of the
remedy have been implemented in accordance with applicable enforcement
documents and the ROD.
Participants include the State, EPA, and the oversight contractor.
For long-term cleanups, the treatment system(s) must meet the OP&S
criteria.
IV-C Preliminary Close Out Report (PCOR) [top]
The PCOR
focuses on all operable units at the site, including a description
of releases at the site, site conditions, all construction activities
(including removals), completion of construction, five-year reviews,
and a detailed schedule of steps remaining for site completion.
The draft PCOR
is prepared by DOE and should be submitted to EPA before the Final
RA
Report for the final operable unit is completed.
This sequence is typical because the RA
Report may take up to 90 days for DOE to submit and get approved.
Once prepared, DOE must send the draft PCOR
to the EPA Regional coordinator for review and comments. At this
time EPA Headquarters may also comment on the PCOR.
After addressing any of these additional comments, the PCOR
is signed by the appropriate regional official and a copy of the
signed PCOR
is forwarded to EPA Headquarters. The date that the PCOR
is signed is also the trigger for the policy five-year review.
IV-D Preparing the Final RA
Report for the Last Operable Unit [top]
DOE is the lead agency and as the lead agency DOE should prepare
the last RA
Report in consultation with EPA and the State.
The final RA
Report usually contains ten sections and these sections should be
tailored to the site depending upon the type of remediation used.
(The final RA
Report is no different than any other RA
Report.) For example, section VII. Operation and Maintenance activities
would not apply for excavation and off-site disposal. Even if construction
completion has already been achieved, the Region must still ensure
that a Final RA
Report is prepared for the final operable unit. The sections in
the report are as follows:
IV-E Submitting the Final RA
Report to EPA [top]
When the report is received at the EPA Regional Office, EPA uses
the following criteria to approve the Report:
- All construction activities are complete, including site restoration;
- All cleanup goals as specified in the ROD
have been achieved;
- A contract final inspection or equivalent has been conducted;
and
- The RA
Report is consistent with the EPA guidance,
Close Out Procedures
for National Priorities List Sites.
IV-F Final RA
Report Approval [top]
EPA will return the report with the signature (of the Branch Chief
or above) on the cover sheet or by letter to DOE. At the operable
unit level, EPA Headquarters does not have to review the report
or concur with the EPA region.
Once the designated Regional EPA Official approves in writing the
Final RA
Report, this CERCLA
milestone has been accomplished.
IV-G Construction Completion [top]
The completion of the last response action at a site determines
when it becomes eligible for construction completion. At sites requiring
remedial action in the final operable unit, the construction completion
milestone is achieved when:
- A pre-final inspection for the last RA
has been conducted; and
- The designated Regional EPA Official signs the Preliminary Close
Out Report (PCOR) and sends a hard copy to EPA Headquarters.
Construction completion criteria are satisfied when only minor
“punch list” items are identified in the pre-final inspection.
Examples of minor punch list items that will still
allow a construction completion determination include:
- Revegetating landscape (except when integral remedy component);
- Removing construction debris;
- Installing support equipment, such as security lighting;
- Repairing poorly installed flashing on roof;
- Repairing other minor defects in workmanship or construction;
- Demobilization activities;
- Installing additional monitoring wells; and
- Resurfacing roads.
IV-H Site Completion [top]
Site completion signifies the end of all response actions. Site
completion means that the response actions at the site were successful
and no further Superfund response is required to protect human health
and the environment. A site must meet all the criteria below to
be eligible for site completion:
- Cleanup goals specified in all RODs
or removals are met;
- Institutional controls are in place;
- All RA
Reports, On-Scene Coordinator Reports, and Pollution Reports have
been completed;
- All RODs, ROD Amendments, and Explanation of Significant Differences
have been completed;
- The site is protective of human health and the environment;
and
- The only remaining activities at the site are operation and
maintenance.
IV-I Final Close Out Report (FCOR) [top]
Site completion is documented through a FCOR.
The FCOR
documents compliance with statutory requirements and provides a
consolidated record of all removal and remedial activities for the
entire site. Since it is the final record, the FCOR
must be complete and be able to stand alone.
The FCOR
describes how the cleanup was accomplished and provides the overall
technical justification for site completion. The information included
in the FCOR
should be readily available from previous documents such as the
RI/FS,
the RODs,
the RDs,
RA
reports, and the PCOR.
IV-J Approval of the FCOR [top]
Currently, EPA has Regional Coordinators assigned to act as primary
reviewers of the FCOR.
These individuals will work closely with DOE in performing completion
activities and will review the draft FCOR
(along with the State). After addressing EPA and State comments
and obtaining the signature of the Regional Administrator, a copy
of the signed report is sent to EPA Headquarters and to DOE. Once
this is completed, this CERCLA
milestone is accomplished.
|