CERCLA Remedial Action Site Closure Guidance
Figure 5. Type C: Typical Waste-in-Place Remedial
Strategy for CERCLA
Operable Units
Contents:
III-C. Type C: Waste-in-Place
Type C addresses remedies that result in waste remaining on site
after cleanup is complete (i.e., waste-in-place) at CERCLA
operable units. Waste-in-place remedies typically include landfill
cap and landfill cap enhancements; but may also apply to ground water
remedies that do not result in unrestricted use. They are often
performed to prevent, or significantly reduce, the migration of
contaminants. Figure 5 depicts the standard remedial action completion
elements for waste-in-place treatments. To find out more about these
requirements, simply click on the section of the process that is
of interest to you.
C.1 Remedial Action [top]
The RA
is the implementation of the remedy selected in the Record of Decision
(ROD). The RA
start date is defined as the date the contractor has mobilized and
begun substantial and continuous physical on-site remedial action,
as documented by a memo or letter to EPA. Also, this is the start
date of the statutory five-year review for operable units with waste-in-place.
C.2 Operating Properly and Successfully (OP&S) [top]
OP&S
activities are conducted after the physical construction of the
treatment system is complete. The purpose of OP&S
is primarily to test the treatment system. This ‘testing period’
could last up to one year. OP&S
start and finish times should be documented with EPA and the State.
No OP&S
is necessary if no waste is left on-site (Excavation and Off-Site
Disposal). The phrase "operating properly and successfully"
involves two separate concepts. A remedial action is operating "properly"
if the treatment system is operating as designed. That same system
is operating "successfully" if its operation will achieve
the cleanup levels or performance goals (removal of contaminant)
as described in the decision document. Additionally, in order to
be successful, that remedy must be protective of human health and
the environment. For instance, an ex-situ pump and treat system
may be operating properly according to its design for pumping and
extracting so many gallons of ground water per day, but not operating
successfully because the amount of contaminant removed does not
meet the requirements as described in the ROD.
C.3 Final Inspection [top]
With any RA
construction contract, normal construction industry practice is
to conduct contract pre-final and final inspections prior to closing
out the construction contract. These inspections are conducted to
determine whether the treatment system has been completed in accordance
with the contract design and specifications. The inspections are
generally held between the contracting party (DOE) and the construction
contractor, although others can be invited (e.g., EPA).
During the contract pre-final inspection, the contracting party’s
project manager and the construction contractor inspect all elements
of work to see if the work is complete and ready for acceptance
under the terms of the contract. Some minor defects may come to
light as the inspection proceeds. The construction manager develops
a “punch list” of all items that need correction or
completion before the work can be accepted. A pre-final inspection
report is prepared, including the punch list, completion dates for
outstanding items, and a date for a final inspection.
If punch list items are minor, the pre-final inspection may automatically
serve as the final inspection. Otherwise, a final inspection is
conducted later to determine that punch list items are corrected
and all work has been completed in accordance with the contract
plans and specifications. Federal Facility Agreements (FFAs) generally
require a set of inspections to determine that all aspects of the
remedy have been implemented in accordance with applicable enforcement
documents and the ROD.
Participants include the State, EPA, and the oversight contractor.
The inspection can be done concurrently with the contract final
inspection. For long-term cleanups, the treatment system(s) must
meet the OP&S
criteria.
C.4 Preparing the Final RA
Report [top]
DOE is the lead agency and as the lead agency DOE should prepare
the Final RA
Report in consultation with EPA and the State.
The RA
Report usually contains ten sections and these sections should be
tailored to the site depending upon the type of remediation used.
For example, section VII. Operation and Maintenance activities would
not apply for excavation and off-site disposal. Also, the final
contract inspection must be completed before the report can be written
and submitted to the appropriate EPA Regional official. The sections
in the report are as follows:
C.5 Submitting the Final RA
Report to EPA [top]
Following completion of the final contract inspection, submit the
Final RA
Report to the designated EPA Regional Official. The goal is for
DOE to submit the report for approval within 90 days of the final
inspection for OP&S.
When the report is received at the EPA Regional Office, EPA uses
the following criteria to approve the Report:
- All construction activities are complete, including site restoration;
- All cleanup goals as specified in the ROD
have been achieved;
- A contract final inspection or equivalent has been conducted;
and
- The RA
Report is consistent with the EPA guidance,
Close Out Procedures
for National Priorities List Sites.
C.6 Final RA
Report Approval [top]
EPA will return the report with the signature (of the Branch Chief
or above) on the cover sheet or by letter to DOE. At the operable
unit level, EPA Headquarters does not have to review the report
or concur with the EPA region.
Once the designated Regional EPA Official approves in writing the
RA
Report, this CERCLA
milestone has been completed.
C.7 Operation and Maintenance (O&M) [top]
O&M
are the activities required to maintain the effectiveness and integrity
of the remedy. In the case of waste-in-place remedies, O&M
involves maintaining engineered containment structures; operating
leachate and gas collection systems; monitoring to ensure that the
remedy is performing as expected and the environment is protected;
and maintaining and enforcing institutional controls and access
restrictions.
The DOE may have to perform O&M
indefinitely for remedies that contain wastes on-site, or include
institutional controls. Prior to the termination of the O&M,
EPA approval is required.
C.8 Statutory Five-Year Review [top]
Statutory five-year reviews generally are required following implementation
of remedial actions selected under Section
121 of CERCLA,
when hazardous substances, pollutants, or contaminants remain on-site
above levels that allow for unlimited use and unrestricted exposure
(as is the case for waste-in-place remedies). In contrast, policy
five-year reviews generally are appropriate for sites where completion
of the remedial action ultimately will allow for unlimited use and
unrestricted exposure, but the remedy will take longer (many years)
to reach cleanup levels as specified in the ROD.
The purpose of the five-year review is to evaluate the implementation
and performance of a remedy in order to determine if the remedy
is or will be protective of human health and the environment. Five-year
reviews provide an opportunity to identify potential problems or
issues with the remedial action and adjust O&M
where necessary.
However, coordinating the timing of both statutory and policy reviews
for DOE will be challenging because many of the DOE’s response
actions are being implemented at large, complex sites which have
been organized into Waste Area Groups (WAGs) or many operable units
(Oak Ridge, for example, has over 400 operable units). When multiple
WAGs
or operable units ‘trigger’ a review at a site, DOE’s
preference is to combine all of these reviews into a single “site-wide”
five-year report. Initially, doing so may mean that for some WAGs
and/or operable units the first review occurs sooner than five years
from the start of the remedial action. However, reporting all WAGs/operable
units for the site at the same time in one site-wide report would
eliminate the need to track an excessive number of different reporting
dates and should reduce the time and cost associated with reporting
five-year reviews.
In March of 2002, DOE, in conjunction with EPA, issued guidance
on conducting five-year reviews entitled, Comprehensive Environmental
Response, Compensation and Liability Act (CERCLA)
Five-Year Review Guide. Refer to this guidance before conducting
and preparing your five-year review.
C.9 Check List for Type C-Waste-in-Place [top]
- Remedial Action
- Operating Properly and Successfully
- Pre-Final Inspection
- Punch List
- Final Inspection
- Final RA
Report
- Preparing the Final RA
Report
- Submitting the Final RA
Report
- Final RA
Report Approval
- Operation and Maintenance
- Statutory Five-Year Review
|